It took nearly five weeks of heating the furnace before Kamoa-Kakula cast its first copper anodes. The first concentrate went into the furnace on 21 December 2025. The first anodes came off the casting line on 29 December, at the mine site west of Kolwezi.

At Makutano Mining 2026 in Kinshasa on 24 November, Kamoa Copper chairman Olivier Binyingo recalled how the project began. Investors funded drilling before they knew how large the deposits would prove to be. Ivanhoe Mines dates the Kamoa discovery to 2008 and Kakula to 2016. Investment reached US$7 billion after the second discovery, Binyingo said. That figure covers development of the complex, including the smelter and work on infrastructure owned by the national power utility, SNEL.

The mine entered commercial production in July 2021. Earthworks for the smelter followed in 2022 as part of an expansion that also added a third concentrator. Processing more concentrate on site means Kamoa-Kakula can now ship some of its copper as 99.7%-pure anodes. Ivanhoe says switching from concentrate to anodes more than doubles the amount of copper each truck can carry.

The furnace also needed a reliable power supply. Before feeding in the first concentrate, the team installed a 60 MW backup system designed to take over during grid disturbances. Binyingo also pointed to the investment in SNEL’s infrastructure. Some of the extra electricity made available by that work stays on the grid for other users, he said.

The smelter was designed to produce 500,000 tonnes of copper a year. In its third-quarter 2026 results, Ivanhoe said it was running at about 60% of design capacity, in line with concentrate production. With the furnace operating, the pace of the ramp-up depends on how much concentrate the mine can supply.